Idaho Public Utilities
Commission
Case No. IPC-E-11-08,
Order No. 32380
October 14,
2011
Contact:
Gene Fadness (208) 334-0339, 890-2712
Website: www.puc.idaho.gov
Settlement would
increase Idaho Power rates by 4 percent
Rate
case hearings set in American Falls, Gooding and Boise
Parties to
an Idaho Power Company rate case have reached a settlement that, if approved,
would increase rates an average 4 percent, down from the nearly 10 percent
requested by the company when it filed its application June 1.
The
proposed settlement must be approved by the Idaho Public Utilities Commission,
which has scheduled public hearings in American Falls on Nov. 3, in Gooding on
Nov. 9 and in Boise on Dec. 5.
The
proposed settlement would allow Idaho Power an annual revenue requirement
increase of $34 million. The utility originally sought $83 million, or an
average overall rate increase of 9.9 percent.
Included in
the proposed average 4 percent increase is an increase in the monthly service
charge from $4 to $5 per month. The new
rates, if approved, would become effective Jan. 1. The parties are proposing a 7.86 percent rate
of return. The company sought 8.17 percent.
Parties signing
the settlement include commission staff, the Idaho Irrigation Pumpers
Association, the Industrial Customers of Idaho Power, the Department of Energy,
Micron Technology, the Idaho Conservation League, the Snake River Alliance, the
Northwest Energy Coalition and Hoku Materials. The Community Action Partnership
Association of Idaho, which represents customers on low- and fixed-incomes,
participated in the settlement discussions but not sign largely because Idaho
Power has not agreed to increase its funding for a low-income weatherization
program.
The signing
parties agreed to defer and amortize over four years a nearly $300,000 expense
for a turbine inspection. They also propose to defer $436,000 for a Light
Detection and Ranging survey and amortize that over 10 years. That deferral and
amortization mitigate the size of rate increases for customers.
Some issues
were not resolved and will be argued during the Dec. 5 technical hearing while
others will be handled separately in other cases.
Issues to
be argued during the technical hearing include the amount of funding that Idaho
Power should provide for a low-income weatherization program; the surcharge
level for the Energy Efficiency Rider (now set at 4.75 percent of billed rates)
and the method used to calculate facilities charges for large commercial and
industrial customers.
The issues
to be handled separately include the amount paid by parties requesting a line
extension and whether the annual pilot Fixed Cost Adjustment (FCA) mechanism
should be made permanent.
The
commission will conduct three public hearings, giving customers an opportunity
to testify regarding the proposed settlement. Those hearings will be:
·
Thursday, Nov. 3, at 7 p.m. in the Power County
Courthouse Annex, 500 Pocatello Ave., in American Falls.
·
Wednesday, Nov. 9, at 7 p.m. at the Gooding County
Planning and Zoning Building, 145 Seventh Ave. East in Gooding.
·
Monday, Dec. 5, at 7 p.m. at the commission hearing
room, 472 W. Washington St. in Boise.
The
technical hearing will also be Dec. 5 beginning at 9:30 a.m. in the commission
hearing room.
The
commission cannot, by state law, arbitrarily refuse to consider utility rate
increase requests without first considering the evidence presented by the
utility, intervening parties and customers. The burden of proof is on the
utility to justify the expenses it seeks to recover through rates as 1) necessary
to serve customers and 2) prudently incurred. The commission may accept, reject or modify
the company’s request. All commission
decisions can be appealed to the state Supreme Court by the utility,
intervenors or customers.
Continued
growth in demand for electricity, aging infrastructure and higher compliance
and reliability requirements are the driving factors behind the rate increase
request, according to the company’s application.
Idaho Power
claims it has made significant investment in pollution control equipment in
four units and upgraded a turbine in one unit of the Jim Bridger power plant, a
coal-fired facility in southwest Wyoming.
The company plans additional investment at its Valmy coal plant in
Nevada this year. Idaho Power also completed construction of a new 500-kilovot
Hemingway transmission station and the associated Hemingway to Bowmont 230-kV
transmission line at a total cost of $54 million. The company also completed construction of
the Long Valley Operations Center in Lake Ford to replace the existing McCall
Operations Center.
The
company’s application further states that the cost of building materials has
increased dramatically since the last time the company was granted a general
rate increase in 2009. In that two-year
period, the company claims aluminum costs have increased 59 percent; copper,
104 percent and standard plate steel, 83 percent.
To mitigate
the size of the increase, Idaho Power says it is not including nearly $32
million in power supply expenses and also is not asking for construction
expenses related to the Hells Canyon relicensing project. While not collecting the expenses now will
impact cash flow, it will not affect the company’s earnings or perception of
the company’s financial health in the markets, according to Greg Said, vice
president for regulatory affairs.
Idaho Power
serves nearly 500,000 customers in southern Idaho and eastern Oregon.
Customers
can track the case on the commission’s Web site, www.puc.idaho.gov., where the company’s
application, including testimony from company officials and intervening parties
as well as customer comments are posted. Click on the electric icon, then on
“Open Electric Cases,” and scroll down to Case No. IPC-E-11-08.
###