Idaho Public Utilities Commission
Case No. IPC-E-10-37, Order No. 32159
January 13, 2011
Contact: Gene Fadness (208)
334-0339, 890-2712
Website: www.puc.idaho.gov
Commission adopts agreement with
hydro project near Filer
The Idaho Public Utilities
Commission has approved a 10-year sales agreement between Idaho Power Company
and J.M. Miller Enterprises, the Michigan-based developers of the 0.5-megawatt Sahko
Hydro Project near Filer.
The project was already selling energy, but
under a different tariff schedule. This proposed sales agreement is a PURPA
agreement. The Public Utility Regulatory
Policies Act of 1978 requires electric utilities to offer to buy power produced
by qualifying small-power producers or co-generators. The rate to be paid
project developers, called an “avoided cost rate,” is to be equal to the cost
the electric utility avoids if it would have had to generate the power itself
or purchase it from another source. The
commission must ensure the avoided-cost rate is reasonable for utility
customers because 100 percent of the price utilities pay to qualifying
producers is included in customer rates.
During this year, the agreement’s
rate for normal load hours during normal seasons of the year is $60.06 per
megawatt-hour, escalating to $87.40 per MWh in 2020.
The rate varies to account for heavy and light load hours of the day and heavy
and light load seasons of the year.
A full text
of the commission’s order, along with other documents related to this case, is
available on the commission’s Web site at www.puc.idaho.gov.
Click on “File Room” and then on “Electric Cases” and scroll down to Case
Number IPC-E-10-37.