Idaho Public Utilities Commission
February 18, 2011
Case No. IPC-E-10-45, Order No. 32181
Contact: Gene Fadness (208) 334-0339,
890-2712
Idaho Power renews agreement
with Jerome area hydro project
The Idaho
Public Utilities Commission has approved an Idaho Power Company agreement to
buy power from the 8.1-megawatt Hazelton A
Hydroelectric Project near Jerome. The
project is already constructed and generating power. Its developer, SE Hazelton
of Andover, Mass., has had an agreement with Idaho Power since 1989. That
agreement expired on Dec. 31, 2010.
Even though
the facility will continue to use its existing interconnection and transmission
facilities and capacity, Idaho Power will require completion of a Generator
Interconnection Agreement and Transmission Service Requests in order to bring
the facility up to date with Idaho Power’s current tariffs and processes.
The
project is a Qualified Facility under the provisions of the federal Public
Utility Regulatory Policies Act (PURPA) passed by Congress during the energy
crisis of the late 1970s. PURPA requires electric utilities to offer to energy
produced by small-power producers who obtain Qualifying Facility (QF) status. The rate to be paid project developers, called
an “avoided cost rate,” is determined and published by state commissions. The
avoided cost rate is to be equal to the cost the electric utility avoids if it
would have had to generate the power itself or purchase it from another source.
The commission must ensure the avoided-cost rate is reasonable for utility
customers because 100 percent of the price utilities pay to qualifying
producers is included in customer rates.
The
agreement is for 15 years beginning Jan. 1, 2011. In 2011, the agreement’s rate
for normal load hours during normal seasons of the year is $60.06 per
megawatt-hour, escalating to $103.76 per MWh in 2025.
The rate varies to account for heavy and light load hours of the day and heavy
and light load seasons of the year.
A full text of the commission’s order, along with other documents related to this case, is available on the commission’s Web site at www.puc.idaho.gov. Click on “File Room” and then on “Electric Cases” and scroll down to Case No. IPC-E-10-45.