Idaho Public Utilities Commission
Case No. GNR-E-11-01, Order No.
32195
February 25, 2011
Contact: Gene Fadness (208)
334-0339, 890-2712
Website: www.puc.idaho.gov
Commission outlines process for
small wind, solar case
The Idaho Public Utilities
Commission has established a schedule in a case seeking the best way to allow
small wind and solar developers to qualify to be paid commission posted rates.
On Feb. 7, the commission ruled
that wind and solar project developers who want to be paid the commission
posted rate can be no larger than 100 kilowatts during the period that this
case is processed. Previously, projects up to 10 megawatts could qualify for
the published rate. The 10 MW upper limit remains for non-wind and non-solar
renewable projects.
Parties who want to intervene in
the case for the purpose of presenting evidence and cross-examining witnesses
must file petitions to intervene with the commission by no later than March 4.
Those parties who were part of the previous docket leading up to this case
(GNR-E-10-04) are automatically included as intervenors in this case.
Pre-file direct testimony and
exhibits will be accepted through March 25 with rebuttal testimony and exhibits
due April 22. The commission will then conduct a technical hearing beginning
Tuesday, May 10, at 9:30 a.m. in the commission hearing room, 472 W. Washington
St. in Boise. The hearing may continue, if necessary, through May 13.
Idaho’s three major regulated electric
utilities – Idaho Power Company, Avista Utilities and PacifiCorp – contend that
a rapidly expanding number of wind projects is having a profound impact on
customer’s rates and reliability. The utilities contend that large-scale wind
farms are breaking up their projects into smaller 10-MW increments in order to
qualify for the published rate, which is typically more attractive than rates
for projects larger than 10 MW.
The published rate is called an
“avoided-cost rate” because it is to be based on the cost the utility avoids by
buying power from the small-power producer and, thus, not having to build the
generation itself or buy power from another source.
Small-power producers can have
their projects declared Qualifying Facilities (QFs) under the provisions of the
federal Public Utility Regulatory Policies Act (PURPA) passed by Congress in
1978 to promote the development of renewable energy technologies. PURPA
requires electric utilities to buy power generated by QFs at the avoided-cost
rate determined by state commissions. Commissions must publish avoided-cost
rates for projects with a design capacity of 100 kW or less. However, the
commission has the discretion to set the published rate at a higher amount and,
until recently, the commission has established a 10 MW eligibility cap.
The commission must ensure the
avoided-cost rate is reasonable for utility customers because 100 percent of
the price utilities pay to QFs is included in customer rates. Federal rules
regulating PURPA development insist that rates for purchases from QFs be “just
and reasonable to ratepayers and in
the public interest – not in the interest of the QFs,” the commission stated in
its Feb. 7 order.
The three utilities claim the
small-power projects PURPA was originally intended to encourage are now often
developed by sophisticated large-scale wind farms that break up, or disaggregate,
large wind projects into several smaller projects in order to qualify for the
published avoided-cost rate. When combined, these projects can total up to 100
or 150 MW interconnecting at one delivery point. The rapid expansion of these
projects is causing a strain on utility transmission systems which can affect
electric reliability, the utilities claim.
On Feb. 7, the commission said the
utilities made a “convincing case,” to temporarily reduce the eligibility cap
for wind and solar projects only until these issues can be resolved. The 100-kW
cap does not include all types of renewable projects, such as biomass, hydro,
geothermal and anaerobic digestion, because these types of projects do not pose
the same type of issues as those posed by wind and solar. The latter two are
intermittent and must be backed-up by other generation when the wind does not
blow or when the sun does not shine. Further, large-scale wind and solar
projects can be broken up into smaller projects to qualify for the published
rate.
In this case, the commission is soliciting
information and investigation of an avoided-cost rate cap structure that allows
wind and solar QFs that are 10 MW or smaller to again qualify for published
rates while also preventing large QFs from disaggregating their projects to
qualify for a rate exceeding true avoided cost.
“The commission is supportive of all
small-power producers contemplated by PURPA, including wind and solar, and it
is not the commission’s intent to push small wind and solar QF projects out of
the market,” the commission said in its Feb. 7 order.