Idaho Public Utilities Commission
Case No.
PAC-E-10-07, Order No. 32196
March 1,
2011
Contact:
Gene Fadness (208) 334-0339, 890-2712
Website: www.puc.idaho.gov
Commission issues final order in Rocky
Mountain Power rate case
The
Idaho Public Utilities Commission has released its final order in a Rocky
Mountain Power (RMP) rate case that began last May. In late December, the
commission issued an interim order that established new rates for all customer
classes that became effective Jan. 1, 2011, but still had issues to resolve
regarding the utility’s largest customer, the Monsanto Company plant in Soda
Springs.
The
68-page order addresses the Monsanto issues and provides the findings to
support the late December decision to grant the company an overall 6.78 percent
increase in its annual revenue requirement, or $13.75 million. When the company
filed its application last May, it asked for a 13.7 percent increase, or $27.7
million. After technical hearings, the company lowered its request to 12.3
percent or $24.9 million.
The 6.78 percent
average increase is offset by a decision to reduce customers’ Energy Efficiency
Charge from 4.72 percent to 3.4 percent, resulting in a net average increase
for residential customers of about 5.5 percent. The net amount of actual
increase varies by class of customer and by usage. For example, with the new two-tiered
rate design approved by the commission in this case, a residential customer
using RMP’s average consumption of 839 kilowatt-hours per month will realize a
1.5 percent decrease. The two-tiered rate structure increases rates as
consumption increases, with residents paying more after the first 700 kWhs of
use in the summer and after the first 1,000 kWh in the winter. The rates for
the first tier are actually lower than the company’s previous rates.
From May to
October, standard residential customers will pay 9.58 cents per kWh for their
first 700 kWhs. The former May-October rate was 10.4 cents. For use exceeding
700 kWhs during summer, the new rate is 12.9 cents.
During the winter
season (November through April) residential customers will pay 7.33 cents per
kWh for the first 1,000 kWhs. The former winter rate was 8 cents. For use above
1,000 kWhs, the rate is 9.9 cents.
Part of the average
6.8 percent annual increase in rates is a customer service charge that varies
according to customer class and is added to cover metering and billing expense.
For most residential customers that charge is $5. The company requested $12.
Many of the
customer comments opposed RMP’s proposal to increase the standard residential
rate by 8 percent, while residential customers who are on the company’s Time of
Day program would pay 15.6 percent more. The commission determined to assign an
equal percentage increase for both residential customers of 6.78 percent.
The largest reductions
the commission made in RMP’s request (addressed in detail later in this press
release) include 1) allocating $11.4 million in expense for the company’s
irrigation load control program to the utility’s entire six-state system and
not just to Idaho customers; 2) reducing RMP’s requested allowable rate of
return from 8.36 percent to 7.98 percent and its requested Return on Equity
from 10.6 percent to 9.9 percent; 3) allowing only 73 percent of the company’s
investment in the Populus to Terminal (Downey to Salt Lake City) transmission
line and putting the remaining 27 percent in plant held for future use; and 4) disallowing
in rates all wage increases awarded by the company to employees during 2009 and
2010 as well money for the company’s Supplemental Executive Retirement Plan.
Removing wage increases does not necessarily mean employee increases will be
withdrawn, but that the cost would not be paid by customers.
“In making these adjustments
we address concerns raised by parties and customers and acknowledge the
economic conditions and service requirements in the company’s southeastern
Idaho service territory,” the commission said. The commission conducted two
workshops, four public hearings, two technical hearings and a telephonic
hearing. Nearly 100 people testified and the commission also received more than
200 written comments.
Regarding RMP’s
request for an increased rate of return and return on equity, the commission
order states:
“We find that RMP (Rocky Mountain
Power) in this case downplayed the poor economic conditions that exist in its
Idaho service territory where many are on fixed incomes, unemployed and
underemployed. This commission cannot discount as simply anecdotal the
testimony and comments of RMP customers. While we cannot say ‘no’ to a
requested increase in rates because customers are uniform in their opposition,
together their testimony serves as the real-life context and backdrop of our
decision. Their testimonies and comments remind us that we are not engaged in
simply an academic exercise dealing in regulatory principles, generalities and
industry averages. Our decision has real consequences.”
However, the
commission said it also has statutory obligations to balance the interests of both
customers and company to ensure a financially healthy utility that can provide
reliable service and plan for future needs:
“We recognize that for some
customers any increase may result in economic hardship. That being said, we have
a dual obligation in rate cases. To customers our task is to establish rates
that are fair and reasonable. To the company we have a statutory obligation to
set rates at a level sufficient to allow RMP to recover its reasonable expenses
of operation and receive a reasonable return on prudent capital investments in
utility plant and facilities. Carrying out this duty is necessary for the
company to be financially sound and capable of providing its customers with
safe and reliable electric service.”
When
the commission denies cost recovery to a utility, it must be able to legally
demonstrate why the utility’s costs were not prudently incurred or in the best
interest of customers. All commission decisions can be appealed to the state
Supreme Court.
Rocky Mountain
Power is a division of PacifiCorp, which operates in six states and is in the
midst of a multi-year program of investing in renewable energy, transmission
facilities and environmental controls to serve the growing demands of its
customers in Idaho and across its system. The company claimed that its
system-wide expenses during 2009 include over $4 billion of new plant
investment and $87 million in increased power costs. Those expenses are then
allocated among the six states based on each state’s electrical load, which for
Idaho is about 6 percent of PacifiCorp’s total system load. Expenses that
cannot be demonstrated to benefit Idaho customers are not included in the rates
Idaho customers pay.
The case was
extended for an additional technical hearing to consider changes to Monsanto
Company’s agreement with Rocky Mountain Power that allows the utility, under
specified circumstances, to curtail its power delivery to Monsanto to meet
other customer needs. Monsanto has a total load of 182 megawatts, but up to 173
MW can fall under the interruptible portion of the agreement. The
interruptibility provisions of the agreement are significant because electric
rates are a substantial portion of production costs at the elemental
phosphorous plant and also because Monsanto’s economic vitality has a large
impact on the economy of Soda Springs and the surrounding area.
The electric
service agreement between Monsanto and RMP allows the utility to curtail
electric delivery to Monsanto under any of these three circumstances: 1) to
allow the utility to meet mandated reserve requirements, 2) for economic
reasons – as when market prices for electricity allow RMP to save money for
itself and its customers – and 3) to interrupt for system integrity to avoid
outages. The agreement limits the number of megawatts that can be curtailed and
the number of hours that curtailment can happen for each of the three
circumstances.
RMP proposed
significant reductions in the amount it said it would pay Monsanto for the
interruptions. Monsanto disputed the value the company placed on the interruption
services. In today’s order, the commission established values for each of the
three interruptibility products that are higher than those proposed by RMP but
less than those proposed by Monsanto. The actual numerical values are proprietary.
The commission also encouraged the parties to craft an agreement that
establishes the value of the products for five years rather than three years.
The commission said the longer agreement would promote greater price certainty
for Monsanto as well as allow RMP to plan more effectively into the future.
The commission’s
order also directs RMP to increase its annual funding for low-income
weatherization in Idaho from $150,000 to $300,000 and to increase the dollar
amount of RMP funds available for each weatherization project from 75 percent
to 85 percent of total eligible costs. The commission noted there is a
five-year backlog of homes that need and are eligible for weatherization in
southeastern Idaho.
The order issued today is final. The
order can be accessed on the commission’s Web site at www.puc.idaho.gov. Click on “File Room,” in
the upper-left hand corner of the page, then on “Recent Orders and Notices,” to
click on Order No. 32196 dated Feb. 28.
Parties to the case or interested
persons can petition for reconsideration by no later than March 21. Petitions
for reconsideration must set forth specifically why the petitioner contends the
order is unreasonable, unlawful or erroneous. Petitions should include a
statement of the nature and quantity of evidence the petitioner will offer if
reconsideration is granted. Petitions can be delivered to the commission at 472
W. Washington St. in Boise, mailed to P.O. Box 83720, Boise, ID, 83720-0074, or
faxed to 208-334-3762.
Below is a more detailed summary of
the commission’s finding on some of the major issues in this case:
Irrigation
load control program costs
The Idaho
Irrigation Load Control program pays credits to irrigation customers who agree
to have their service curtailed during times of peak demand. In 2007, the
program provided 78 megawatts to the company, but by 2009 that had grown 250
percent to provide 276 megawatts of demand reduction for the company. The
nearly $20 million in savings benefits PacifiCorp customers in all six states
and, therefore, the $11.4 million cost of the program should be allocated system-wide
and not just to Idaho customers, the commission ruled. Doing that removes $3.25
million in Idaho annual revenue requirement for RMP and also allows a reduction
to the Energy Services Rider paid by customers from 4.72 percent to 3.4
percent.
“We find that it is
unreasonable to expect Idaho customers to continue to bear the costs associated
with the current jurisdictional treatment of the Irrigation Load Control
Program expenses,” the commission said.
Rate of return, return on equity
The rate of return
is the amount the company is allowed the opportunity to earn on its capital
investment. The company requested 8.357 percent and was granted 7.98 percent. The
return on equity is the rate of return equity investors expect given the risks
of an individual security and consistent with returns that are available from
similar investments. The company requested 10.6 percent and was granted 9.9
percent. Setting the allowable rate of return and return on equity is not a
guarantee the company will reach those levels, but caps the returns at the
commission’s authorized level.
The commission uses
three primary standards in determining rate of return. The authorized return
should be 1) sufficient to maintain financial integrity, 2) attract capital
under reasonable terms and 3) be commensurate with returns investors could earn
by investing in other enterprise of comparable risk. The rate of return must be
enough to attract capital investment in new transmission, distribution and
generation but not so high as to be unreasonable for customers.
The commission
cited current economic conditions in southeastern Idaho as a primary factor in
reducing the company’s requested return on equity to 9.9 percent.
Populus to Terminal Transmission Line
The line, which
runs from Downey to Salt Lake City, is the first of eight proposed new
high-voltage transmission segments that will make up PacifiCorp’s Energy
Gateway transmission expansion project. The line benefits Idaho customers in
that it is intended to add 1,400 MW of transmission capacity to an already
heavily constrained area and allows the company access to less costly
generation sources.
However, the
commission ruled that because the company can use only about 1,040 MW of the
total capacity, Idaho’s portion of the full cost should not be included in
rates until the entire 1,400 MW is available to customers. Therefore, the
commission placed 27 percent of the transmission investment into Plant Held for
Future Use. “Idaho, we find, will pay its fair share to meet the company’s
system load and transmission requirements but we will not allow full ratebasing
of investment in Populus to Terminal prematurely and we will not require Idaho
customers to assume and pay for unused capacity.”
Wages and pensions
Wage increases
awarded employees in 2009 and 2010 cannot be included in rates, reducing
revenue requirement by almost $1 million. The commission’s order states:
“The Commission finds that in tough
economic times the local economy in the Company’s service area is a greater
indicator as to the appropriateness of a wage increase than market data and
industry averages. We find no
demonstration by the Company that the union and non-union wage increases were
required for the Company to be a competitive employer able to retain or attract
employees. We find no offer of proof
that without the union and non-union wage increase the service provided by the
Company would be degraded and safety compromised. We find that as a certificated provider of
service RMP has elected to be a member of the communities it serves.”
The commission also
disallowed recovery of costs related to RMP’s Supplemental Executive Retirement
Plan. “The company has not demonstrated that these costs are related to
providing services to southeast Idaho,” the commission said. “The
responsibility for generous severance benefits for executives, we find, is the
responsibility of the company and its shareholders, not Idaho customers.”
Intervenors in the
case who provided testimony and rebuttal and
cross-examined witnesses during technical hearings included Monsanto Company,
the Idaho Irrigation Pumpers Association, the Idaho Conservation League, PacifiCorp
Idaho Industrial Customers, the Community Action Partnership Association of
Idaho and commission staff.
####