Idaho Public Utilities
Commission
March 16,
2011
Case No.
IPC-E-11-01, Order No. 32203
Contact:
Gene Fadness (208) 334-0339, 890-2712
Idaho Power seeks PUC decision regarding
Oreana wind project
Comments
are being accepted through April 7 on an Idaho Power Company application for
state regulators to accept or reject a sales agreement with a 5-megawatt wind
project near Oreana.
The
developer of the project, Boise-based Western Desert Energy LLC, seeks a
20-year agreement with a scheduled operation date of Dec. 1, 2012. The
agreement states that the project developer would be paid by Idaho Power at a
rate that is published by the Idaho Public Utilities Commission.
However,
the application for the projects was submitted to the commission after the Dec.
14, 2010, effective date of a commission order that reduced the eligibility cap
on the size of wind and solar projects that can qualify for the commission’s
published rate from 10-megawatts to 100 kilowatts.
Idaho’s
three major investor-owned electric utilities asked the commission to
temporarily reduce the eligibility cap on projects that can qualify for the
commission’s published rate while the commission examines issues surrounding the
rapid development of large wind projects that are broken up into smaller 10-MW
projects in order to qualify for the published rate. The utilities claim the
disaggregation of the wind projects is circumventing their planning processes
and creating system reliability and operational issues. Idaho Power claims that
the “continuing and unchecked requirement” for the utility to acquire
additional intermittent generation regardless of its need for additional energy
“increases the price its customers must pay for their energy needs.”
Despite
those concerns, Idaho Power states it is complying with its federal mandate
under the Public Utility Regulatory Policies Act (PURPA) to accept power
generated from qualifying renewable facilities. (The reduction in the eligibility cap does not waive regulated
utilities’ PURPA requirement to buy energy from wind and solar projects, but
the rate paid to projects larger than 100 kW will now be negotiated between the utility and the
developer using the published rate as a starting point for negotiation.)
PURPA
was passed by Congress in 1978 to encourage development of renewable energy
technologies as alternatives to burning fossil fuels or building new power
plants. The act requires that electric utilities offer to buy power produced
from qualifying small-power producers at rates determined by the states. The
rate to be paid small-power developers, called an avoided-cost rate, is to be
equal to the cost the utility avoids if it would have had to generate the power
itself or purchase it from another source.
The
commission must ensure the avoided-cost rate is reasonable for utility
customers because 100 percent of the price utilities pay to qualifying
producers is included in customer rates.
Western
Desert Energy seeks to be paid a non-levelized rate
that increases through the life of the contract. In 2013, the published rate
for normal load hours during normal seasons of the year is $61.93 per
megawatt-hour, escalating to $125.89 per MWh in 2033.
The rate varies to account for heavy and light load hours of the day and heavy
and light load seasons of the year.
The
agreement states that it is up to the wind developer to work with Idaho Power’s
business delivery unit to ensure that interconnection facilities and
transmission upgrades are completed in time to meet the projects’ scheduled
operation date. If the projects fail to meet their delivery dates, delay
damages will be assessed.
Comments are
accepted via e-mail by accessing the commission’s homepage at www.puc.idaho.gov and clicking on
"Comments & Questions About a Case." Fill in the case numbers
(IPC-E-11-01) and enter your comments. Comments can also be mailed to P.O. Box
83720, Boise, ID 83720-0074 or faxed to (208) 334-3762.
A full text of the commission’s order, along with other documents, is available on the commission’s Web site. Click on “File Room” and then on “Electric Cases” and scroll down to the above case number.