Idaho Public Utilities Commission
Case No. PAC-E-11-06,
Order No. 32235
May 3, 2011
Contact:
Gene Fadness (208) 334-0339, 890-2712
Website: www.puc.idaho.gov
Parties settle on changes to
irrigation load control program
The Idaho
Public Utilities Commission has accepted a settlement proposed by Rocky
Mountain Power, eastern Idaho irrigators and commission staff that will result
in less drastic changes to the company’s irrigation load control program than
those originally proposed by the company.
Rocky
Mountain Power’s Dispatchable Irrigation Load Control program, in place since
2007, allows the utility, during periods of peak demand, to turn off the pumps
of irrigators who volunteer to participate. In exchange, irrigators received a
credit of $30 per kilowatt. Pumps can be turned off for periods of time during
June through August from 11 a.m. to 7 p.m. as long as the utility provides
prior-day notification and as long as total curtailment for any participant
does not exceed 52 hours.
On Jan. 20,
Rocky Power filed an application to change the program because of voltage
problems created by rapidly expanding participation in the program. When the
program began in 2007, participating load totaled 65 megawatts, but that
increased to 278 MW in 2010. The company claimed that much curtailment was creating
voltage control problems with circuits at four substations experiencing
unacceptable increases. To respond, Rocky Mountain wanted to reject prospective
program participants and reduce the credit irrigators receive from $30 per kW to
$25.30. The company also proposed to
modify the penalty irrigators receive for opting out of scheduled curtailments.
Irrigation
customers as well as commission staff objected to some of the proposed changes.
A negotiated settlement by commission staff, the Idaho Irrigation Pumpers
Association and the company will allow the utility to limit program
participation to 232 MW for the next two years, or an 18 percent reduction.
Further, the $30 per kW credit to each irrigator will be reduced by $1.45 for
this season only to account for 11 MW of unobtainable curtailment due to the
voltage issues at four substations. In the meantime, the company agreed to
invest a minimum of $1.3 million in capital improvements to install equipment
needed to address the issues at the four substations before the start of the
2012 irrigation season.
During the
two-year period of this settlement, new participants or additional load
reduction from existing participants will not be accepted. Volunteer irrigators
can decline to participate in some of the curtailments, but the credit they are
paid by the company is reduced for each curtailment incident for which the
irrigator decides to opt out.
The Idaho
Conservation League also participated in the settlement discussions. It did not
sign the settlement but does not oppose it.
To read the
commission’s final order or other documents related to the case, go to www.puc.idaho.gov. Click on the electric
icon, then on “Open Electric Cases,” and scroll down to Case No. PAC-E-11-06.