Idaho Public Utilities
Commission
Case No.
IPC-E-12-14, Order No. 32585
June 29,
2012
Contact:
Gene Fadness (208) 334-0339, 890-2712
Website: www.puc.idaho.gov
Natural gas plant
expense is allowed in rates
The Idaho
Public Utilities Commission is allowing Idaho Power Company to increase its
annual revenue by $58 million to pay for a $400 million natural gas plant scheduled
to be online Saturday.
Average
rates will increase by 6.8 percent to pay for the 330-megawatt Langley Gulch
natural gas plant four miles south of New Plymouth. For an Idaho Power customer
who uses 1,020 kilowatt-hours per month, the average monthly bill will increase
by $5.63, from $82.72 per month to $88.35.
The
commission determined in 2009 that the additional resource would be needed to
meet customer demand and granted Idaho Power a Certificate of Public
Convenience and Necessity (CPCN) to build the plant. “The company has a
statutory obligation to provide electric service and, since 2004, has forecast
a need for a baseload generation resource in 2012,” the commission said when it
granted the CPCN three years ago. The purpose of the 2012 case is to review the
company’s expenditures in building the plant.
While the
total cost of the plant is $401.4 million, today’s order allows $389.4 million
in base rates. About $7.2 million was included
in rates during the company’s 2011 general rate case and another $3.23 million
will be incurred after June 30 and so must be included in a future rate case.
Commission
staff performed a detailed review of the company’s application and workpapers
that included a comprehensive audit of the actual and estimated plant and
transmission expenditures. The
commission approved these adjustments:
n
Removed
$300,000 that Idaho Power requested for a contingency fund to resolve potential
issues after June 30;
n
Removed
$251,894 in costs related to the bid process to construct the plant;
n
Removed
$1.2 million in expense related to an upgrade in the Langley to Wagner transmission
line from 183 kV to 230 kV and placing it in a Plant Held for Future Use account
for possible recovery later. The commission said the $1.2 million should not be
placed in rates now because the additional capacity “is not associated with the
near-term operation of the Langley plant. This investment is associated with
the future generation and transmission needs of the company.”
n
Removed
$75,000 in costs for splicing fiber optic cable that will not be incurred until
after June 30.
Parties
filing comments in the case included the Industrial Customers of Idaho Power
(ICIP), the Idaho Irrigation Pumpers Association, the Snake River Alliance and
commission staff, along with 11 customers.
Both ICIP
and the irrigators argued Idaho Power is experiencing declining load growth
since the CPCN was granted in 2009. ICIP
expressed concern that the low cost of operating the Langley plant would reduce
use of the company’s three coal-fired plants by 70 percent.
The
irrigators said the commission should schedule a full rate case to review the
gas plant’s impact on Idaho Power’s overall system given changing
conditions. In the alternative, the
irrigators said, the commission should grant no more than half the increase and
require Idaho Power to file a general rate case. The Snake River Alliance argued that
construction of the plant “was and continues to be ill-timed,” and said Idaho
Power has ample energy supplies, particularly so with the failure of both the
Hoku polysilicon plant in Pocatello and the Micron-Transform Solar project in
Nampa.
In its
reply comments, Idaho Power acknowledged a decline in load of 1.5 percent, but
said that without the Langley plant the company’s peak-hour loads would still
reflect a projected deficit of 28 megawatts next month, 169 MW in July 2013 and
224 MW in July 2014. The company
maintained that ICIP did not take into account Idaho Power’s use of its coal
plants during below-average water years.
Further, the company argued, the availability of Langley will
significantly reduce the company’s reliance on purchased power.
Regarding
the temporary condition of declining load, the commission said it is “not
afforded the use of hindsight to judge the reasonableness of issuing the CPCN
to Langley three years ago. However, it is interesting to note that ICIP argued
in the prior CPCN case that Langley would be an expensive plant to operate but
now maintains Langley, ‘will be Idaho Power’s least expensive unit, on a
variable cost basis.’ “
The
commission said granting half the increase, as requested by the irrigators,
undermines the commission’s 2009 order when it issued the CPCN and would
violate the statutory binding ratemaking treatment included in that same order.
The pre-approved amount included in that order was necessary to facilitate the
financing of the Langley plant, the commission said.
The
commission noted that it attempts to balance the interest of the utility and
ratepayers and reduced the requested rate base commitment by $26 million to
protect ratepayers.
A
full text of the commission’s order, along with other documents related to this
case, is available on the commission’s Web site at www.puc.idaho.gov. Click on “File Room”
and then on “Electric Cases” and scroll down to Case No. IPC-E-12-14.
Interested parties may petition the
commission for reconsideration by no later than July 20. Petitions for
reconsideration must set forth specifically why the petitioner contends that
the order is unreasonable, unlawful or erroneous. Petitions should include a
statement of the nature and quantity of evidence the petitioner will offer if
reconsideration is granted.
Petitions can be delivered to the
commission at 472 W. Washington St. in Boise, mailed to P.O. Box 83720, Boise,
ID, 83720-0074, or faxed to 208-334-3762.